Wightlink carries out essential maintenance at Fishbourne

Wightlink will be carrying out essential maintenance work at its berth at Fishbourne port from Monday 29 March to Friday 14 May 2021.

Aging fenders will be replaced with new ones in four weeks of overnight work, scheduled to take place when tides permit.

Wightlink Chief Executive Keith Greenfield says “Our contractors will do their best to keep disturbance to a minimum but unfortunately, there may be some noise. We apologise in advance if this causes any inconvenience to our neighbours in Fishbourne.”

Contractors will be based on a barge offshore during the operation. The replacement work will be suspended if winds rise over 25 knots.

Schedule of fender works at Fishbourne

DatesScheduled work
Monday 29 March – Friday 2 April Berthworks 20:00-05:00
Monday 5 April – Friday 9 April No works because of tides
Monday 12 April – Friday 16 April Berthworks 20:00-05:00. The 23:00 and 01:00 sailings from Fishbourne will be cancelled on 13 and 14 April
Monday 19 April – Friday 23 April No works because of tides
Monday 26 April – Friday 30 April Berthworks 20:00-05:00
Monday 3 May – Friday 7 May No works because of tides
Monday 10 May – Friday 14 May Berthworks 20:00-05:00. The 23:00 and 01:00 sailings from Fishbourne will be cancelled on 11 and 12 May